CONSTRUCTION
- Dirt Subcontractor completed building pad undercut; we are nearing completion on the parking lot undercut.
- Remaining storm drainage, all the materials are on site.
- We have completed installing Geopiers.
- This process required drilling deep into the ground, placing casing, and pouring crushed gravel in all piers.
- Foundation
- Wealth Tech Solutions was contracted for Electrical and Plumbing.
- Plumbers completed underground rough-in within 4 days.
- Electrical rough-in has started and will be completed in 6 days.
- Concrete Subcontractor has mobilized and began setting form boards for the foundation. Elevator pit forming is completed.
- We expect to have foundation pour completed by 2nd week of February.
- General Items
- Windows contract has been signed and are in production
- Elevator has been signed.
- Wealth Tech Solutions was contracted for Electrical and Plumbing.