JANUARY

CONSTRUCTION

  • Dirt Subcontractor completed building pad undercut; we are nearing completion on the parking lot undercut.
    • Remaining storm drainage, all the materials are on site.
  • We have completed installing Geopiers.
    • This process required drilling deep into the ground, placing casing, and pouring crushed gravel in all piers.
  • Foundation
    • Wealth Tech Solutions was contracted for Electrical and Plumbing.
      • Plumbers completed underground rough-in within 4 days.
      • Electrical rough-in has started and will be completed in 6 days.
    • Concrete Subcontractor has mobilized and began setting form boards for the foundation. Elevator pit forming is completed.
      • We expect to have foundation pour completed by 2nd week of February.
    • General Items
      • Windows contract has been signed and are in production
      • Elevator has been signed.