MARCH

CONSTRUCTION

  • Pool
    • Pool contractor is complete with gunite application to the pool.
  • Viking (Sitework)
    • Sitework to begin their grading and installation of asphalt base this week .
  • Framing

    • Framers have completed fur down in the bathrooms on floor 2,3 and 4.
  • Sprinkler
    • Currently working on 1st floor corridors.
  • Mechanical, Electrical, Plumbing

    • Mechanical
      • 4,3 and 2 floor inspections have passed.
      • They will start running trunk lines and installing AAON Shaft this week.
    • Electrical
      • Inspection passed on 3 and 4th
      • 2nd floor inspection this Friday.
      • Transformer has been installed on site and we are getting ready for Permanent power on site.
    • Plumbing
      • They have finished everything on 4,3,2 and are working on the first floor.
  • EIFS / Stucco
    • We are currently finished with 50% of EFIS installation. Contractor is moving to the back side now that the pool is complete.
  • General Items
    • Close up inspections were completed on 4th and 3rd.  2nd floor Scheduled for this Friday.
    • Insulation to be on site for 4th and 3rd floor and installed this weekend.
    • 4/1/25 we will start installing sheetrock on 4th and 3rd floor
    • Elevator to be on site 5/29
    • Guestroom FFE to be delivered 5/31