CONSTRUCTION
- Pool
- Pool contractor is complete with gunite application to the pool.
- Viking (Sitework)
- Sitework to begin their grading and installation of asphalt base this week .
- Sitework to begin their grading and installation of asphalt base this week .
- Framing
- Framers have completed fur down in the bathrooms on floor 2,3 and 4.
- Sprinkler
- Currently working on 1st floor corridors.
- Currently working on 1st floor corridors.
- Mechanical, Electrical, Plumbing
- Mechanical
- 4,3 and 2 floor inspections have passed.
- They will start running trunk lines and installing AAON Shaft this week.
- Electrical
- Inspection passed on 3 and 4th
- 2nd floor inspection this Friday.
- Transformer has been installed on site and we are getting ready for Permanent power on site.
- Inspection passed on 3 and 4th
- Plumbing
- They have finished everything on 4,3,2 and are working on the first floor.
- Mechanical
- EIFS / Stucco
- We are currently finished with 50% of EFIS installation. Contractor is moving to the back side now that the pool is complete.
- General Items
- Close up inspections were completed on 4th and 3rd. 2nd floor Scheduled for this Friday.
- Insulation to be on site for 4th and 3rd floor and installed this weekend.
- 4/1/25 we will start installing sheetrock on 4th and 3rd floor
- Elevator to be on site 5/29
- Guestroom FFE to be delivered 5/31