FEBRUARY/MARCH

CONSTRUCTION

  • Dirt Subcontractor
    • Dirt Subcontractor is working on grading the parking lot and getting it ready to do form and pour concrete. We are doing a concrete parking lot on this site instead of asphalt. SENT
    • Storm drainage is completed on the North, South, and West side. They are working diligently to finish the East side.
  • Concrete Subcontractor
    • Concrete Subcontractor has successfully completed waterproofing the elevator pit, excavating and forming exterior footing, installing anchor bolts, and installing rocks for the foundation pour.
    • The foundation pour was completed on 3/12
    • Concrete Subcontractor has battled through the rain in the month of February, but we got the building pad poured.
    • We currently have concrete reports that shows all concrete placed has met the specifications.
  • Site Subcontractor
    • Site subcontractor has started installing the utilities on the west side
    • Fire line valve was installed by the City of Ruston
    • We have successfully completed the retaining wall on the west side.
  • Red Iron( Steel)
    • All red iron has been erected and installed on this job.
  • Framing Subcontractor
    • Framing subcontractor has completed framing the first floor.
    • We have lumber deliveries for each floor slated every week.
    • Framing subcontractor has started installing trusses for the second floor.
  • Electrical Subcontractor
    • Electrical Subcontractor has completed the temporary power to the building.
    • Wealth Tech Solutions have started running the conduits for primary power.
    • Electrical Subcontractor is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
  • Plumbing Subcontractor
    • Wealth Tech Solutions has completed setting the grease trap and installation of fire riser.
    • Plumbing subcontractor is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
  • Mechanical Subcontractor
    • Lake Mechanical is contracted for Mechanical work.
    • Lake Mechanical is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
  • Fire Sprinkler Subcontractor
    • VFP is contracted for Fire Sprinkler work.
    • VFP is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
  • General Items
    • Windows are in production and scheduled to be on site by end of April
    • PTAC contract has been signed and sample PTAC sleeve and drain kit is on site.
    • Doors and hardware contract has been signed.