CONSTRUCTION
- Dirt Subcontractor
- Dirt Subcontractor is working on grading the parking lot and getting it ready to do form and pour concrete. We are doing a concrete parking lot on this site instead of asphalt. SENT
- Storm drainage is completed on the North, South, and West side. They are working diligently to finish the East side.
- Concrete Subcontractor
- Concrete Subcontractor has successfully completed waterproofing the elevator pit, excavating and forming exterior footing, installing anchor bolts, and installing rocks for the foundation pour.
- The foundation pour was completed on 3/12
- Concrete Subcontractor has battled through the rain in the month of February, but we got the building pad poured.
- We currently have concrete reports that shows all concrete placed has met the specifications.
- Site Subcontractor
- Site subcontractor has started installing the utilities on the west side
- Fire line valve was installed by the City of Ruston
- We have successfully completed the retaining wall on the west side.
- Red Iron( Steel)
- All red iron has been erected and installed on this job.
- Framing Subcontractor
- Framing subcontractor has completed framing the first floor.
- We have lumber deliveries for each floor slated every week.
- Framing subcontractor has started installing trusses for the second floor.
- Electrical Subcontractor
- Electrical Subcontractor has completed the temporary power to the building.
- Wealth Tech Solutions have started running the conduits for primary power.
- Electrical Subcontractor is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
- Plumbing Subcontractor
- Wealth Tech Solutions has completed setting the grease trap and installation of fire riser.
- Plumbing subcontractor is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
- Mechanical Subcontractor
- Lake Mechanical is contracted for Mechanical work.
- Lake Mechanical is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
- Fire Sprinkler Subcontractor
- VFP is contracted for Fire Sprinkler work.
- VFP is scheduled to start first floor rough in when the framing subcontractor is framing third floor.
- General Items
- Windows are in production and scheduled to be on site by end of April
- PTAC contract has been signed and sample PTAC sleeve and drain kit is on site.
- Doors and hardware contract has been signed.